Draw a triangle on the whiteboard of almost any transformer oil laboratory and nobody needs an explanation. Three corners, a few zones, one plotted point — and a fault type falls out. That small piece of geometry has been steering dissolved gas analysis (DGA) interpretation for roughly fifty years, and the man behind it is Duval Michel, the Canadian researcher whose name has become shorthand for the method itself. What follows is a practical walk through who he is, how the triangle actually works, where it earns its keep, and where it quietly runs out of road.
Michel Duval spent a large part of his career at Hydro-Québec's research institute, IREQ, near Montreal, studying the chemistry of insulating oil and the gases it releases when something inside a tank begins to misbehave. In the 1970s he proposed an elegantly simple alternative to staring at six gas numbers in a table and arguing about them: normalise three hydrocarbon gases to 100 percent, plot the result as a single point inside a triangle, and let the zone name the fault.
The idea survived because it worked. The method was refined over the following decades — later work by Duval added Triangle 4 for low-temperature faults and stray gassing, Triangle 5 for on-load tap changers, and eventually the Duval Pentagon, which handles five gases at once. The original triangle now sits inside IEC 60599 and alongside IEEE C57.104 in day-to-day diagnostic practice. In laboratories from Hai'an to Houston, a plot of three gases is still the fastest way to say "this looks like arcing" or "this looks like overheating".
Mineral oil breaks down in fairly predictable ways. When it is heated, or when a discharge passes through it, long hydrocarbon chains crack into smaller molecules, and the mix depends on how much energy was involved. Three of those molecules do most of the diagnostic work:
Duval's practical insight was that absolute concentrations matter less than the balance between them. So the chart uses percentages of the sum of the three, for example %CH4 = 100 × CH4 ÷ (CH4 + C2H4 + C2H2), with the same arithmetic for ethylene and acetylene. Hydrogen, ethane, carbon monoxide and carbon dioxide are deliberately left out — they carry real information, but folding them in would blur the picture the triangle is designed to sharpen.
Each corner of the chart is 100 percent of one gas. The zone boundaries were drawn from field data on hundreds of failed units, which is why they look empirical rather than mathematical: they are. Six zones do the everyday work, with a seventh added in later revisions.
| Zone | Typical pattern | What it usually means |
|---|---|---|
| PD | Methane dominant, often above 98 percent | Partial discharge in a gas void |
| D1 | Low but clear acetylene | Low-energy discharge or sparking |
| D2 | High acetylene share | High-energy arcing, often destructive |
| T1 | Ethylene rising, methane still strong | Thermal fault below 300 °C |
| T2 | Ethylene dominant | Thermal fault between 300 and 700 °C |
| T3 | Ethylene very high | Thermal fault above 700 °C |
| DT | Mixed pattern near a boundary | Combined thermal and electrical fault |
The method names a fault type. It does not measure severity, and it certainly does not decide whether a unit stays energised. The same plotted point on a twenty-year-old distribution transformer and on a new 220 kV unit can mean two very different things, because absolute gas levels, loading history and rate of change all differ. Three habits keep the interpretation honest:
There is one blind spot worth naming. Triangle 1 only reveals partial discharge when methane dominates the three plotted gases, so an early, hydrogen-rich discharge can sit quietly in the healthy centre of the chart. If hydrogen is climbing while the point stays put, a different instrument — Triangle 4 — is the better choice. We go deeper into sampling and interpretation routines in our DGA testing guide.
The original chart was never meant to be the last word, and the family has grown to cover the cases the first triangle handles awkwardly.
| Method | Gases used | Best suited to |
|---|---|---|
| Triangle 1 | CH4, C2H4, C2H2 | General fault typing on mineral-oil transformers |
| Triangle 4 | CH4, C2H4, C2H2 plus H2 and C2H6 | Low-temperature faults, stray gassing, confirming partial discharge |
| Triangle 5 | CH4, C2H4, C2H2 in tap-changer oil | On-load tap changer compartments, which have their own gas behaviour |
| Pentagon | H2, CH4, C2H6, C2H4, C2H2 | Five-gas fault typing and cross-checking a triangle result |
In daily practice, most laboratories plot Triangle 1 first because it is quick and widely understood, then reach for Triangle 4 or the pentagon when the answer is ambiguous or when hydrogen tells a different story than the three plotted gases.
Charts are useful; decisions are better. The triangle matters most when it feeds maintenance planning on assets that cannot simply be swapped out — a mine feeder transformer, a substation in a coastal industrial park, a compact prefabricated substation serving a residential block. A D2 reading that reaches the right engineer quickly can turn a rewinding job into an oil treatment and a re-test, or turn a potential failure into a planned shutdown.
Because of that, gas interpretation sits close to how the equipment itself is built. On our oil-immersed distribution transformers, oil is sampled and tested before dispatch and the baseline results travel with the unit, so an owner has something meaningful to compare against in year five and year fifteen rather than starting from zero.
Oil-Immersed Distribution Transformers from 30 to 3150 kVABrowse sealed oil-immersed distribution transformer options, including amorphous alloy and oil-pillow designs, with capacity and voltage ranges for distribution applications.View Product →
At the larger end, the same discipline applies with higher stakes. A 110 kV or 220 kV power transformer holds thousands of litres of oil and sits at the centre of a network, so commissioning baselines, first-year sampling intervals and trend records belong in the handover package rather than in an afterthought.
110 kV Ultra-High Voltage Power Transformer, 5 MVAFor higher-stakes transmission projects, this 5 MVA 110 kV transformer supports long-distance power transmission with reduced losses and custom/OEM options.View Product →Michel Duval's contribution was not a new sensor or a new instrument; it was a way of thinking clearly about numbers that were already sitting in front of people. Half a century later, that is still the most useful thing a diagnostic method can do. If you are commissioning new equipment, chasing a gas trend, or simply want a second opinion on a plot that looks ambiguous, our engineers are glad to look at it with you — get in touch and bring the sample history.
Contact Us